Project Overview
The design for this project utilized two 1600kW CAT engines for a total of 3.2MW. The Newkirk/Theka team provided complete design and installation of the engine generation station and controls, as well as designed and constructed the substation-utility interface. The team integrated the design with the existing design in the original plant for the gas compression/cleanup station.
Project: Grand Blanc Landfill Gas to Energy Plant
Type: Landfill Gas
Location: Grand Blanc, Michigan
Role: Design-Build Contractor